Development and service of drilling fluid

The inclined interval which include nonproductive carbon layers was cased. The interval was drilled with using Polymer Inhibited Mud System PIDM-2M.

The next step is penetration of pay zone. It will be run through the use of clayless drilling mud system Biocar®

 

PARAMETERS OF DRILLING MUD BEFORE LINER RUNNING:
  • Density – 1,20-1,24 g/сm3;
  • Funnel Viscosity – 75-90 s;
  • Gel – 70/80-80/90 dPa;
  • PV – 29-34 mPa*s;
  • YP – 90-140 dPа;
  • Filtration loss – 5,0-5,5 сm3/30 min.;
  • Mud Cake Friction Coefficient – 0,1-0,14;
  • КСl – 5,0-6,0%;
  • Salinity – 10-11%;
  • рН – 9,5-10,0.